The old shopping precinct at Craig Croft, Chelmsley Wood
-
May 2007 - Solihull Metropolitan Borough Council grants outline planning permission for a new £30m Village Centre at Craig Croft
-
July 2011- planning permission for phase 1 & 2 of Village Centre (Enterprise Centre, Improvements to
Chester Road, Village Centre roads & public realm) is granted and £4.3m of external funding secured
-
The unpopular underpass will be filled in & a new Toucan crossing created on the Chester Road
-
March 2011 - SMBC grants planning permission for new Bishop Wilson C of E Primary School
-
April 2012 - Building work on the new £10m Bishop Wilson school & adjoining St Andrews Church progress
-
on the site of the new Enterprise Centre
April 2013 - work on phase 1 & 2 of the regeneration of Chelmunds Cross gets underway
-
June 2013 - Warwick Court during a £30 million programme
to reclad & install Biomass boilers at 37 high rise blocks in North Solihull
-
September 2013 - The new Bishop Wilson School opens to pupils
-
November 2013 - work begins on improvements to the Chester Road
-
February 2014 - progress on the Enterprise Centre
-
March 2014 - the old precinct gets demolished
-
June 2014 - the carriageway on the Chester Road is reduced to a single lane and a 40mph speed limit introduced
-
New carpark & infrastructure works on Hedingham Grove
-
June 2014 - Completed Junction
-
July 2014 - a new road, Pomeroy Way, opens as part of the Village Centre for the first time
-
July 2014 - Phase 1 & 2 of the regeneration of Chelmunds Cross is complete, total cost £9.1m
-
The old NHS clinic & dental practice gets demolished
-
January 2015 - Phase 3 of the regeneration of Chelmunds Cross;
development of the new £3.5 million health centre is underway
-
August 2015 - Health Centre progress
-
June 2015 - after undergoing extensive refurbishment Three Trees Community Baptist Church includes a café & gardens
-
November 2015 - Croft Medical Centre opens to patients
incorporating a GPs practice, pharmacy & dental practice
-
August 2016 - Phase 4 work progresses on the new Co-operative retail & office accommodation above
-
October 2016 - progress on the retail development
-
September 2016 - Phase 5 work starts on the development of a new specialist care home (artists impression)
-
June 2017 - The new Co-operative retail store opens to the public & Solihull Council occupy the offices above
-
September 2017 - progress on the specialist care home
-
September 2017 - progress on the specialist care home
-
October 2017 - work on the specialist care home is complete
-
November 2017 - the new 73 bed specialist care home is officially opened.
This completes the £30m regeneration of Chelmund's Cross Village Centre